The A-1 Total Service Plumbing team spent their day in the City of La Palma working with Javier Jimenez from MJC Construction on mainline point repairs. A-1TSP is performing ten 8-inch point repairs and two 10-inch Sectional Point Repairs to be completed by Wednesday. Today in La Palma, we performed all!
We pre-CCTV inspected all mainline point repairs and installed two 8-inch by 8FT repairs and one 8-inch by 11FT all INF runners within the first 4FT of the manhole. These mainline point repairs were quick and easy, tomorrow will be the hard part!
My son Michael in the manhole, he’s getting up to speed on mainline point repairs!